St. George's I-15 Widening: Every Road Project by Status and What Buyers Should Check
UDOT expects to start widening I-15 between Bluff Street and St. George Boulevard in November 2026, with two new underpasses and work running into 2029. Here is every St. George area road project by status, who is affected now, where the noise walls go and how to check a lot against planned corridors.

Interstate 15 has two lanes in each direction for the 2.5 miles between Bluff Street and St. George Boulevard, and for most of that distance there are only a few places to get from one side of the freeway to the other. The Utah Department of Transportation (UDOT) is about to change both. Its project page says construction on a third lane each way, replacement bridges and two new underpasses is expected to begin in November 2026 and run through spring 2029.
That is the largest of several road projects around St. George. Some have crews on site, some have money and a start date, and some are lines on a long-range map or tied up in federal court. This article sorts them by status, using UDOT, city and Dixie Metropolitan Planning Organization pages and local news reports.
What the I-15 Project Includes
UDOT lists the work between Bluff Street (Exit 6) and St. George Boulevard (Exit 8) at $175 million. According to the project page, crews will:
- Widen northbound and southbound I-15 from two lanes to three. The new lanes go to the inside, toward the median, to avoid substantial property impacts.
- Replace the bridges at 100 South and 700 South and raise the freeway there.
- Build new bridges over 400 East and 900 South so that both streets can pass under I-15 as local connections, with sidewalks.
- Build two noise walls on the east side of the freeway.
- Improve drainage along I-15 and the cross streets to reduce flooding, and relocate utilities.
One piece is not included. UDOT's 2023 environmental study recommended a new interchange at 700 South, but the agency says it will not build it during this project because of fiscal constraints.
The underpasses nearly fell out as well. An $87.6 million federal grant awarded in 2024 was rescinded in 2025. In March 2026 the Salt Lake Tribune reported that the state was putting $62.9 million from its Transportation Investment Fund into the project and the city $5 million, and in July 2026 St. George received a $23.5 million federal BUILD grant for the two crossings. UDOT's page now states that the project is funded and will be built. Mayor Jimmie Hughes said in the city's announcement that the interstate had "acted as a wall through the heart of St. George."
The finish date depends on which document is read. UDOT's March 2026 construction announcement said winter 2028, and the project page says spring 2029.
Every Project by Status
| Project | What it is | Status in November 2026 | Cost |
|---|---|---|---|
| Bluff Street (SR-18), St. George Boulevard to Main Street | Raised medians, new storm drains in place of the open ditch, intersection upgrades, resurfacing | Under construction. UDOT expects to wrap up in winter 2028 | $38.3 million |
| George Washington Boulevard bridge and extension | New bridge and road extension that complete an east-west route from the Southern Parkway toward the Dixie Drive interchange (I-15 Exit 5) | Under construction since early 2026. The city's target was about summer 2027 | $23.5 million for the bridge |
| Southern Parkway (SR-7) trail | Paved path beside SR-7. First section runs from Exit 2 to Exit 6 | First section scheduled to start construction in summer 2026. Other sections in design or planned | Not listed |
| I-15 widening, Exit 6 to Exit 8, with underpasses at 400 East and 900 South | Third lane each way, four bridges, two noise walls | Funded. Start expected November 2026, finish between winter 2028 and spring 2029 | $175 million |
| New SR-7 interchange near milepost 5 | Ramps and a bridge between River Road (Exit 3) and Desert Canyons Parkway (Exit 6), connecting to a future city road | City project, in design. The city's page lists construction from spring 2026 through spring 2027 | About $15 million |
| I-15 interchange at 700 South | New single-point interchange recommended in UDOT's 2023 study | Deferred. Not funded | Not funded |
| Northern Corridor | Four-lane, 4.5-mile highway from Washington Parkway to Red Hills Parkway through the Red Cliffs National Conservation Area | Halted by a federal court in March 2026 while a lawsuit proceeds | Not listed |
| Western Corridor | Future road on the county's west side, tying Gap Canyon Parkway and Old Highway 91 to the SunRiver area | Long-range plan. An environmental study was reported as funded for 2027 | Not funded |
Dates come from UDOT and city project pages and from St. George News coverage of the February 2026 Dixie Regional Transportation Expo. Schedules are subject to change. On the Southern Parkway, UDOT said at the expo that no large-scale widening is scheduled, only a northbound climbing lane near Sand Hollow Reservoir. On SR-9 through Hurricane, the only current UDOT work is a fiber optic line along the shoulder, with no direct traffic impacts expected. Private development and non-road projects are covered in a wider list of what is being built around St. George.
Who Feels It Now

Bluff Street drivers and businesses. This is the work zone that exists today. In early November 2026, UDOT reported paving throughout the corridor, new sidewalk between 900 South and Main Street and night closures of 800 South for sewer work. The speed limit in the zone is 35 mph with doubled fines. Crews may work days and nights, Monday through Friday.
Central St. George on both sides of the freeway. As of mid-November, UDOT's I-15 page listed no scheduled traffic impacts yet. Once work starts, the streets to watch are the ones with bridges: 100 South, 700 South, 400 East and 900 South. Dixie High School and Dixie Middle School are close to this stretch, and city officials have said the underpasses are meant to give students a safer, more direct route.
Commuters from Washington and Hurricane. Drivers coming from Washington or Hurricane reach this segment at Exit 8. In Washington City, UDOT widened I-15 between Green Springs (Exit 10) and Washington Parkway (Exit 13) and added the Main Street interchange (Exit 11) in a project it expected to finish in 2024.
The south side. The George Washington Boulevard bridge has been a construction site since early 2026, and the first Southern Parkway trail section starts at the I-15 interchange at Exit 2, beside Desert Color. Background on that community is in the Desert Color overview.
Which Areas Gain When It Is Done
Neighborhoods along 400 East and 900 South
Today, crossing I-15 in this part of town means using Bluff Street, 700 South or one of a few other busy points. Two more crossings shorten local trips and, the city's government affairs director told the Salt Lake Tribune, should relieve some congestion on Bluff Street. The trade is more through traffic on both streets. At UDOT's June 2025 open house, some residents opposed the underpasses for that reason, St. George News reported.
The south side of St. George
George Washington Boulevard will form a new east-west corridor between the Southern Parkway and I-15, and the SR-7 interchange near milepost 5 is planned to connect to the 3000 East corridor. Together they give south-side drivers another east-west route and another way onto the Southern Parkway. Current listings are on the St. George homes for sale page, with a separate page for new construction in St. George.
Ivins and Santa Clara: mostly waiting
St. George said in February 2026 that the north segment of Gap Canyon Parkway, from Sunbrook Drive to Canyon View Drive, was a priority to bid, while the south segment was delayed by groundwater. The Western Corridor that would continue toward Old Highway 91 remains a planning item. Buyers in Ivins and Santa Clara should assume today's routes into St. George for the foreseeable future.
The Northern Corridor: Approved, Then Stopped Again
This road has a long paper trail. A 2009 federal law created the Red Cliffs National Conservation Area and addressed a northern transportation route across it, in language that supporters and opponents of the road read differently. The Bureau of Land Management (BLM) controls the land. UDOT applied for a right-of-way in 2018. The sequence since then, as reported by St. George News, KUER and KSL:
- 2021 to 2023: BLM approves the right-of-way in January 2021, conservation groups sue, and a federal court sends the approval back for reconsideration in November 2023.
- December 2024: BLM terminates the right-of-way and endorses widening Red Hills Parkway instead.
- January 21, 2026: BLM reapproves the highway, calling the Red Hills Parkway alternative infeasible.
- February 2026: Six conservation groups file a new lawsuit in Washington, D.C.
- March 1, 2026: A federal judge issues a preliminary injunction barring UDOT from fencing and other construction-related work while the case heads to summary judgment.
Washington County officials have noted that the injunction is not a ruling on the merits. UDOT's page, updated in May 2026, lists only geotechnical work that does not disturb the ground as current. No final ruling had been reported in the sources reviewed. Buyers near Washington Parkway or Red Hills Parkway should treat this road as undecided.
Noise Walls and Other Downsides
- Walls are voted on, and one failed. UDOT balloted residents beside the freeway in 2025. A wall needs 75% of ballots returned and 75% of those in favor. Two 10-foot walls on the east side passed, one from Bluff Street to 700 South and one from 700 South to 100 South. The west-side wall drew 70.17% support, short of the threshold, and will not be built.
- A raised freeway. I-15 will be lifted at four cross streets to fit the bridges, which can change the view and the sound for the closest homes.
- Overlapping work zones. Bluff Street and I-15 will both be under construction for a time, and 400 East and 900 South become through streets afterward.
How to Check a Lot Against a Planned Road
- Read the project page first. UDOT's I-15 St. George page has the map, the noise wall locations under its History tab, and an Impacts and Updates tab for closures. The project hotline is 435-280-2266.
- Open the long-range plan. The Dixie MPO's 2023-2050 Regional Transportation Plan, adopted in May 2023, has an interactive map of planned roads across Washington County.
- Check the city's transportation master plan. St. George, Washington City, Hurricane, Ivins and Santa Clara each plan their own collector and arterial streets. A planned city arterial behind a back fence matters as much as a state highway.
- Visit twice. Once at 5 p.m. on a weekday and once after dark.
- Separate funded from planned. A corridor on a 2050 map, or one in court, may be a decade away or may never be built.
Transit: Small Changes So Far
SunTran, the city-run bus system, lists seven local routes, including Route 5 to Ivins and Route 7 to Washington, plus the 42-mile Zion Route through Washington, Hurricane, La Verkin and Virgin to Springdale. The Zion Route runs Monday through Saturday and costs $5 one way. At the February 2026 expo, a SunTran planner said the agency had broken ground on its own fleet facility on Brigham Road and was starting a transit study to improve routes and reach outlying areas. He acknowledged there are few stops south of the Virgin River. No new routes had been announced.
Where Prices Stand in the Three Cities
| City | Median sale price | Median days on market | Sale-to-list ratio | Active listings |
|---|---|---|---|---|
| St. George | $505,000 | 41 days | 98.1% | 998 |
| Washington | $529,990 | 51 days | 99.0% | 573 |
| Hurricane | $530,900 | 73 days | 98.6% | 461 |
These figures update monthly from MLS data. Why the area keeps needing new roads is covered in St. George's growth explained, and the same funded-versus-planned test is applied to the Wasatch Front in a status check on northwest Utah County's freeways.
Listings in all five cities, with a map view for comparing a home's position to these projects, are on Best Utah Real Estate.
Sources: Utah Department of Transportation project pages and its March 26, 2026 construction announcement; City of St. George SR-7 and SunTran pages; Dixie Metropolitan Planning Organization; St. George News (Feb. 16, 2024; June 28, 2025; Feb. 19 and 21, March 3 and July 17, 2026); Salt Lake Tribune (March 28, 2026); KSL (March 3, March 26 and July 17, 2026); KUER (Jan. 21, 2026); KUTV (Sept. 5, 2025).
Posted by Kristopher Larson
Frequently asked questions
When does the I-15 widening in St. George start and finish?
UDOT's project page says construction is expected to begin in November 2026 and continue through spring 2029. The agency's March 2026 construction announcement gave winter 2028 as the end date, so the finish should be read as a range. As of mid-November 2026 no traffic impacts had been scheduled.
Which part of I-15 is being widened in St. George?
The project covers about 2.5 miles between Bluff Street (Exit 6) and St. George Boulevard (Exit 8). Northbound and southbound I-15 each go from two lanes to three, with the new lanes added toward the median. The bridges at 100 South and 700 South will be replaced and the freeway raised.
Where will the new I-15 underpasses in St. George be?
UDOT will build new bridges over 400 East and 900 South so both streets can pass under the freeway, with sidewalks. They are funded by UDOT, the City of St. George and a $23.5 million federal BUILD grant awarded in July 2026. City officials say the crossings are meant to give students at Dixie High School and Dixie Middle School a safer, more direct route and to take some traffic off Bluff Street.
Will there be noise walls along I-15 in St. George?
Two 10-foot noise walls will be built on the east side of I-15, one from Bluff Street to 700 South and one from 700 South to 100 South. UDOT balloted nearby residents in 2025, and both walls cleared the required 75% return and 75% approval. A proposed wall on the west side received 70.17% support and will not be built.
Is the Northern Corridor highway in St. George being built?
Not at present. The Bureau of Land Management reapproved the right-of-way for the four-lane, 4.5-mile road through the Red Cliffs National Conservation Area on Jan. 21, 2026, but a federal judge issued a preliminary injunction on March 1, 2026 that bars UDOT from construction-related work while a lawsuit proceeds. The injunction is not a final ruling, so the road's future is undecided.
How can a buyer find out if a road is planned near a home in Washington County?
Start with the project page for any UDOT work nearby, then open the Dixie Metropolitan Planning Organization's 2023-2050 Regional Transportation Plan, which has an interactive map of planned roads across the county. Each city also publishes a transportation master plan showing future collector and arterial streets. A project with a budget and a start date is far more certain than a corridor that appears only on a long-range map.
St George, Utah housing market
A quick read on what homes are doing in St George right now — pulled live from the MLS.
Keep reading
More from the blog
St. George's Second Costco Is Open: What New Retail Means for Nearby Neighborhoods and Buyers in 2026
St. George Asking Prices Are 24% Below the 2022 Peak: What Late-2026 Buyers Should Weigh
What $800,000 Buys in St. George and Southern Utah, Town by Town